This Sunday we celebrated National Indigenous Day with songs, drumming, teachings, and cedar brushings.
We saw that the roof is almost complete, siding & windows are expected to be completed by the end of July, landscaping & exterior work is expected to be done by the end of August along with drywalling including mudding & sanding. Electrical & audio/sound rough-ins are expected to be completed by the end of June.
We acknowledged that the Capital campaign has passed the halfway point by putting another marker our signage board. We have raised $ 550,000.00 so far.