March 6 Update. concrete pour for new transept.
Feb. 27th Update
Here’s where we are today:
• building permit dwgs have been submitted. Expect permit to be issued Thursday
• footings for in-ground buttress wall are poured
• perimeter drain is in place around existing footings and is connected to original drains
• weather proofing, rain screen and in-ground insulation is being installed.
• concrete forming materials and rebar are on site for foundation walls
So the re-construction phase has started!